Rehabilitation and Development of Watercourse – Northern State (Phase I)

The project involved rehabilitating and developing the main 40 km watercourse with concrete lining to improve flow efficiency and reduce seepage. Works included over 925,000 m³ of excavation and backfilling, installation of 10 hydraulic and electric gates, 6 reinforced concrete crossings, and construction of a 5 km service road.