Development of Irrigation Pumping Stations – Northern State, Sudan

The project included civil works for rehabilitating three pumping stations (excavation, backfilling, concrete foundations, insulation systems, and administrative buildings), installation of 18 pumps (6 per station, 600 L/s each), construction of a 10 km power supply network with transformers and medium-voltage cables, and hydraulic works including a 35 m feeder canal, filters, valves, and hydraulic testing